10-6 "Pump down" Procedure
10-6-1 MH040FXEA2B/MH052FXEA2B/MH18VF1X/MH19VF1X
Pump down will be carried out when an evaporator is replaced or when the unit is relocated in another area.
1) Remove the caps from the 2 way valve and
the 3 way valve.
2) Turn the 3 way valve clockwise to close and
connect a pressure gauge (low pressure side)
to the service valve, and open the 3 way valve
again.
3) Set the unit to cool operation mode.
(Check if the compressor is operating.)
4) Turn the 2 way valve clockwise to close.
5) When the pressure gauge indicates "0" turn the
3 way valve clockwise to close.
Stop operation of the air conditioner.
6)
7) Close the cap of each valve.
Relocation of the air conditioner
• Refer to this procedure when the unit is relocated.
•
1. Carry out the pump down procedure (refer to the details of 'pump down').
•
2. Remove the power cord.
•
3. Disconnect the assembly cable from the indoor and outdoor units.
•
4. Remove the flare nut connecting the indoor unit and the pipe.
• 4.
At this time, cover the pipe of the indoor unit and the other pipe using a cap or vinyl plug to avoid foreign
material entering.
•
5. Disconnect the pipe connected to the outdoor unit.
• 4.
At this time, cover the valve of the outdoor unit and the other pipe using a cap or vinyl plug to avoid foreign
material entering.
•
6. Make sure you do not bend the connection pipes in the middle and store together with the cables.
•
7. Move the indoor and outdoor units to a new location.
•
8. Remove the mounting plate for the indoor unit and move it to a new location.