FusionModule1000A40 Prefabricated All-in-One Data Center V200R003C10 Commissioning Guide Issue Date 2019-12-20 HUAWEI TECHNOLOGIES CO., LTD.
Page 2
Notice The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS"...
About This Document About This Document Purpose This document describes how to power on and commission the FusionModule1000A prefabricated all-in-one data center (FusionModule1000 for short) in terms of safety precautions, preparations, power-on check, power on commissioning, joint commissioning, power-off, and core device commissioning. It provides you a quick grasp of how to commission the prefabricated all-in-one data center.
The "NOTICE", "WARNING", and "DANGER" statements in this document do not cover all the safety instructions. They are only supplements to the safety instructions. Huawei will not be liable for any consequence caused by the violation of general safety requirements or design, production, and usage safety standards.
Do not power on the equipment before it is installed or confirmed by professionals. 1.2 Personnel Requirements Personnel who plan to install or maintain Huawei equipment must receive thorough training, understand all necessary safety precautions, and be able to correctly perform all operations.
Page 16
Metal shavings from drilling may short-circuit boards inside the equipment. Obtain the consent from the customer, subcontractor, and Huawei before drilling. Wear goggles and protective gloves when drilling holes. ...
Page 19
Commissioning Guide 1 Safety Information To ensure battery safety and battery management accuracy, use batteries provided with the UPS by Huawei. Huawei is not responsible for any battery faults caused by batteries not provided by Huawei. Battery Installation Before installing batteries, observe the following safety precautions: ...
Verify that all devices in the initial configuration table communicate with the management system properly. Check that the views and videos in the management system are consistent with the running status of the data center. If any inconsistency is found, contact Huawei technical support. ----End 7.4 Commissioning the Fire Extinguishing System...
02311FTC-001 Systems Context Perform system commissioning and power-on strictly according to the system manual and ATS instructions. For any changes in operations and parameters, consult Huawei engineers. Otherwise, system commissioning or power-on may fail, or even the cabinet is damaged. Procedure Step 1 Switch on all SPD circuit breakers in the integrated UPS.
Page 64
UPS. During the UPS power-on commissioning, you are not allowed to modify the UPS initial configurations if not authorized by onsite Huawei engineers. UPSs can work in single or parallel mode. Check that the initial configurations are consistent with the configurations in the initial configuration table for the solution in use.
During the MDU power-on commissioning, you are not allowed to modify the MDU initial configurations unless you are authorized by onsite Huawei engineers. Step 3 Enter a user name and password to access the MDU, set the user name, password, time, and language, and check that the initial parameter settings are correct.
Huawei engineers. Step 4 Tap Indicates on the main screen, and tap Confirm on the dialog box that appears. If the start succeeds, the system prompts that the command is successfully executed.
After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the default password in time or password loss after changing.
8.4.1.2 Obtaining the NetEco Software License The NetEco software license is not provided together with software to the customer. Therefore, obtain the NetEco software license in advance. Obtain the license from the Huawei's enterprise support website. For enterprise users: Log into Huawei's enterprise support website http://support.huawei.com/enterprise.
After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
Page 107
VCN IP address in the address box of the Internet browser, and log in to the OMU Portal system. (Optional) Deploying IVS in Stack Mode. For details, log in to the https://e.huawei.com/, search for the VCN510&VCN520&VCN540 Product Documentation, open the documentation, and see the section Deploying IVS in Stack Mode. ...
After the first login, change the password in time to ensure account security and prevent unauthorized network attacks, such as data tampering. Huawei will not be liable for any security issues caused by your failure to change the preset password in time or password loss after changing.
Page 113
Restart Internet Explorer and enter the IP address to be accessed by the client. The page for watching videos is displayed. Click Install according to the prompt message. After the OCX plug-in is installed, you can watch the videos. If videos are not displayed, contact Huawei technical support.